Construction of a new engineering hall on Iowa State University’s campus will continue as designed, but at a significantly higher cost than originally expected.

The Iowa Board of Regents on Thursday approved a new budget for construction of the Therkildsen Industrial Engineering Building — now at a cost of more than $73 million instead of the $54 million approved early in the summer.

The regents on June 2 approved the new four-story building for the industrial and manufacturing systems engineering departments. It will be located northwest of Beyer Hall, 2625 Union Drive. 

At the time of approval, $42 million had been donated by two class of 1959 alumni, C.G. “Turk” and Joyce A. McEwen Therkildsen, whom the building is named after.

A rendering of the Therkildsen Industrial Engineering Building to be built at Iowa State University in Ames shows a view from the southeast. The university received approval June 2 from the Iowa Board of Regents to move forward with the project.

The rest was to be covered by university funds.

More:Iowa State releases new 30-year plan for its buildings, including demolitions, new construction

Heather Paris, the university’s interim senior vice president for operations and finance, told the regents’ property committee this week that when construction proposals were received in August, the projected costs were much higher, reflecting current regional trends.

The original budget predicted a 10% cost increase compared to 2021 prices. But proposals came back last month with a 25% increase, with construction costs alone raising from $39 million to $59 million.